📅 What are the IMO DCS and CII deadlines, including a potential Corrective Action Plan?
Ships subject to IMO DCS must report their annual fuel consumption and other required operational data. Ships subject to CII requirements must also calculate and report their annual attained CII.
|
Deadline |
Requirement |
|---|---|
|
31 March |
Submit the previous calendar year's IMO DCS data to the flag administration or its recognized organization. |
|
31 May |
Verification and issuance of the relevant Statement of Compliance should be completed under the normal IMO DCS timetable. |
|
When required |
Develop a Corrective Action Plan if a ship receives a D rating for three consecutive years or an E rating in any year. |
The Corrective Action Plan forms part of SEEMP Part III and must be submitted for verification within the applicable timeframe.
Audit confirmation required: Confirm the exact Corrective Action Plan submission deadlines and any flag-specific requirements.